Welcome

We developed this blog to provide golf course maintenance information to our members. From projects, small and large, to updates on course conditions, we want to provide as much information as possible. Although we hope this blog answers all of the pertinent questions regarding our operation, we always welcome more personalized dialogue. If you have questions beyond the information found on this blog, feel free to contact our golf course superintendent, Trevor Hedgepeth.

thedgepeth@kinlochgolfclub.com

804-840-8320


Friday, March 10, 2017

#15 Tree Relocation Project - The Tree is Home!!!!


In our last blog post, detailing our tree relocation project, we left off as the tree was being piped and strapped down for the moving process. 



Since that initial post, 16 days ago, a lot has happened. Most importantly, a 75' tall white oak once again resides on our 15th golf hole. As you can see in the photo below, this tree was crucial to the original design intent of this hole. Although a short par 4, the approach to the 15th green hinged on properly negotiating this tree from the teeing area. A misplayed drive could leave you in trouble, but a long, aggressive and accurate drive could leave you with a short pitch for birdie. This particular tree was the "risk" portion of this "risk/reward" par 4. 




Before we walk you through the actual relocation process, I'd like to recognize Erik Hess and his amazing team for an unbelievable job. I'd also like to recognize Lester George, our golf course architect, and Jonathan Ireland, our general manager, for their support and leadership. Finally, I'd like to thank the Kinloch maintenance team for their efforts and the Kinloch membership for their support and patience as we worked to restore the design intent of our 15th hole. This was an unbelievable project that required great teamwork, perseverance and collaboration. At the end of the day, we are very proud of what was accomplished. 

Once the root ball was properly secured and stabilized on top of the piping, Hess Landscaping used 4 large excavators to slide the tree. One excavator was at the rear of the tree to provide a lift and a push, while the other 3 machines were tethered together to make the pull. 


After an initial pull, Hess realized that the root-ball was being very stubborn. So, using very large steel cables, Hess "cable cut" at the base of the root-ball to relieve tension. The tension was so tight due to the tree's weight (300,000 lbs.) that Hess decided to excavate beneath the root-ball to assist in the "cable cut" process. 


Once the root-ball was freed from its old home, the relocation began. As you can see in the picture below, the tree has moved about 10'. 


This picture shows the tree in transit. 


This photo shows our tree from the tee box. As you can see, the tree is pivotal to the golf hole. 


I've included 3 video links below that show the relocation process. 






Wednesday, February 22, 2017

Tree Relocation Update - #15

In our last post, our contractor, Hess Landscaping, had begun excavating the root-ball of a 75' tall white oak tree to be relocated on our 15th hole. To refresh everyone's memory, our 15th hole was designed around a similar tree. We lost that tree back in June during an intense thunderstorm.

 

Since we took the photo above, the root-ball has been fully excavated (see below). To put this project in perspective, that root-ball is 22' in diameter and cut to an average depth of 6'. Doing some math... the root-ball alone is 84 cubic yards and weighs approximately 250,000 pounds. 


Once the root ball was fully excavated, the crew began cutting a road for the tree to slide along. 


 These pipes are driven under the tree on 8" centers. These pipes are 31' long and 5" in diameter. Once installed below the root ball, they will be welded together to form a "raft". 


The tree will be drug along this newly built access road. The road was constructed using the spoils from the root ball excavation. Once the tree is moved, this soil will be cleaned up and used as back-fill for the hole left behind. 


The picture below shows the final destination of the tree. 


More updates to come!! 






Friday, February 17, 2017

Member Update - Tree Relocation #15

Dear Member,

We are pleased to announce the tree transplant project is underway.  The contractor arrived Monday, February 13th and, as you see in the included photo, has begun working to expose the tree’s root ball.  The area being excavated is approximately 22 feet in diameter and as much as eight (8) feet deep.  Over the next two weeks, they will be constructing a box to encapsulate the root ball.  Weather permitting, the contractor plans to conduct the actual relocation on or about March 1st.   The tree, a 70-foot white oak, will be moved from the right side of the 12th hole to the 15th hole and placed in nearly the same location as the previous oak tree lost during a severe storm last June.

Time-lapse cameras have been set up to document the entire process.  Kinloch Superintendent, Trevor Hedgepeth, and his team will also provide periodic updates on the Kinloch Maintenance Blog (www.kinlochgcm.blogspot.com ) as well as our Twitter Feed (@KinlochDaily).  We encourage you to view both areas for informative updates throughout the season.

This transplant is an exciting undertaking.  As we approach and confirm the actual relocation day, we will communicate that information.  We welcome you to visit the club at any time during the coming weeks to view the process firsthand.

We appreciate your support and look forward to seeing you at the club soon.

All the best,
Jonathan Ireland
 

Friday, February 3, 2017

New Walk Trail To #2 Tees

Over the years, the walking trail between the 1st green and 2nd tee has been problematic. Between shade and poor drainage, the grass on this trail has always succumbed to traffic stress over the course of the golf season. In fact, many times in late fall, especially after a rain event, it became not only unsightly, but oftentimes impassable. So, as part of multiple off-season projects, we decided to re-build this trail as a hybrid grass/stone path. Below there are pictures that walk you through the project. The final product is an aesthetically pleasing and sustainable walking trail that should hold up to moisture and the rigors of traffic. 

Step 1: Clear the existing material, lay a base layer (2-3") of drainage sand


Step 2: Lay out the paver stones in the pattern we designed  


Step 3: Recess the paver stones below grade by 1-2" 


Step 4: Sod in between the stones to create a "broken stone" look


One of the main goals with this project was to merge functionality and aesthetics. By choosing a more informal stone design, we believe we have achieved this goal. We hope our members and guests appreciate the improvement to this area.