The New Year brought the completion of our first in-house project of the off season with the addition of a new walk bridge for our members and their guests on the 12th hole. The new grassed walk bridge will make for an easier walk from the Blue tee to the fairway.
Construction began back in the first of December with the stripping of sod and shaping of the existing creek bank leading to the new bridge. A pipe was placed in the creek for continued flow, and then we started forming the new walk bridge above. Once completed, members or our staff constructed a rock wall to border the pipe and frame the bridge.